Piling cost in Bangladesh: Types, rates and cost calculation
Piling is one of the first major costs you may face when building on weak or compressible soil.
But there is no single piling cost in Bangladesh that works for every project.
A 12-inch bored
pile for a small residential building will not cost the same as a 24-inch pile for a heavier
commercial structure. Depth matters too. So do soil conditions, pile diameter, reinforcement,
concrete grade, equipment access, and the number of piles.
This is especially important in Dhaka and nearby areas such as Savar, Gazipur, Narayanganj,
Keraniganj and Rupganj. Ground conditions can change even between nearby plots. A soil test and
structural design therefore come before the final piling budget.
This guide looks at current piling rates, common pile types, and a simple way to estimate the
cost before asking contractors for detailed quotations.
Piling rates in Bangladesh vary considerably between contractors and project locations.
Published contractor estimates provide useful starting figures, but they are not verified market
averages. Some quotations cover only boring, while others include concrete, reinforcement and
additional work. For early budgeting, RCC bored piling can range roughly from Tk 350 to
Tk 1,600
or more per running foot, depending mainly on pile diameter and what the contractor
includes in
the rate.
The rates below are indicative planning ranges. Before using them for your construction budget,
check exactly what each contractor includes.
Pile diameter
Indicative cost per running foot
Approx. cost per running metre
12 inch / 300 mm
Tk 350–600
Tk 1,150–1,970
14 inch / 350 mm
Tk 600–780
Tk 1,970–2,560
16 inch / 400 mm
Tk 550–950
Tk 1,805–3,120
18 inch / 450 mm
Tk 700–1,150
Tk 2,300–3,770
20 inch / 500 mm
Tk 900–1,500
Tk 2,950–4,920
24 inch / 600 mm
Tk 1,200–1,600+
Tk 3,940–5,250+
Note: These figures are approximate planning estimates based on published contractor
references, not fixed rates offered by Conspert Limited. Actual piling costs depend on pile
diameter, depth, soil conditions, materials, site access and the contractor's scope of work. Ask
for an itemised quotation based on your soil investigation and approved structural design.
Types of piling in Bangladesh and their costs
Not every pile type does the same job. Also, bored pile and cast-in-situ pile are
often used as separate terms in online content, although a bored pile is commonly constructed as
a cast-in-situ RCC pile.
Pile type
Indicative pricing
Where it is commonly considered
RCC bored cast-in-situ pile
Around Tk 350–1,600+/rft depending on diameter
Houses, apartments, commercial buildings
Driven precast RCC pile
Around Tk 1,150–1,450/rft for a roughly 400 × 400 mm class public benchmark
Residential, commercial and industrial projects
Micro/mini pile
Around Tk 1,500–2,500/rft in some public market references
Tight sites, strengthening and extension work
PHC pile
Project-specific
Factories, industrial and larger developments
Sheet pile
Material can be Tk 7,000–15,000+/m plus installation
Excavation support, basement and retaining work
Sand pile
Usually quotation-based
Ground improvement rather than normal structural piling
A 2026 market study for Dhaka placed an all-in planning benchmark for roughly 400 × 400 mm driven
precast piles at around Tk 1,150–1,450 per running foot. Government schedule rates also show
that precast pile casting, pile driving, and equipment mobilization can be priced as separate
items.
Sheet piling is mainly used to retain soil, support excavation or control ground movement. It
should not be compared directly with a bored pile carrying a building load. Current public
references in Bangladesh put common steel sheet pile material at roughly Tk 7,000–15,000+ per
metre, with driving or installation charged separately.
Factors that affect piling cost in Bangladesh
The pile rate itself tells only part of the story. A realistic budget needs to look at the full
site condition.
Soil condition and pile depth: Soft upper layers may force the engineer to take the
pile deeper before reaching a suitable bearing layer. More depth means more boring or
driving, concrete, steel, and working time.
Pile diameter: Diameter has a large effect on concrete volume. It may also change
reinforcement requirements and the equipment needed for construction.
Number of piles: A building with 20 piles obviously uses more material than one with
10. However, larger projects may spread rig mobilization costs across more piles.
Structural load: Building height alone does not decide the pile design. Column loads,
layout, structural system and future loading all matter.
Site access: This becomes a practical issue in Dhaka. A narrow road, congested
neighbourhood or restricted working space can make it harder to bring in a drilling rig,
crane, concrete mixer or precast piles.
Groundwater and bore stability: Bored pile work below groundwater may need casing,
drilling slurry or additional control during concreting.
Steel and concrete prices: Piles consume significant reinforcement and concrete.
Changes in these material prices move the final quotation.
Location: Projects outside a contractor's normal equipment area can carry extra
transport, accommodation or mobilization costs.
Piling cost breakdown: Materials, labour and equipment
Before comparing two quotations, check what each contractor has actually included.
Cost item
How it affects the budget
Boring or pile driving
Equipment, fuel, operator, and working time
Reinforcement steel
Steel cage, fabrication, binding, and placement
Concrete
Quantity rises quickly with pile diameter and depth
Casing or drilling slurry
May be needed where the bore is unstable
Labour
Cage preparation, concreting and supporting site work
Mobilization
Moving rig, crane and equipment to and from the site
Testing
Load test, integrity test or other specified tests
Pile head work
Cutting, breaking and preparation before pile cap
Pile cap and grade beam
Normally treated as separate foundation work
This last point causes a lot of budgeting confusion. Piling cost and complete foundation cost
are not necessarily the same thing. A quotation for piles may exclude pile caps, grade
beams, excavation, earthwork and other foundation items.
How soil testing affects piling cost
Do not decide that your house needs a 50-foot or 70-foot pile just because a neighbouring
building used that depth. A soil investigation gives engineers information about the soil layers
and their resistance at different depths. The structural engineer combines this information with
building loads to select the foundation system.
For one plot, a shallow foundation may work. Another site may need bored or driven piles. Even
where both buildings use piles, the diameter, depth and quantity may differ.
That is why a preliminary budget should always be updated after the soil report and structural
design are available.
How to calculate piling cost: Step-by-step example
For a simple first-stage estimate, you can use:
Estimated pile work = Number of piles × Average pile depth × Rate per running
foot
Then add the items that are outside the selected running-foot rate. For example, suppose the
preliminary design for a residential project shows:
16 piles × 55 feet = 880 running feet
If the selected pile is around 350 mm and you use an indicative planning rate of Tk 600–780 per
running foot:
880 × Tk 600 = Tk 528,000
880 × Tk 780 = Tk 686,400
So the basic pile-line budget would be roughly Tk 5.28–6.86 lakh.
This is only a budgeting example, not a foundation recommendation. Mobilization, testing, casing,
pile head work, pile caps, grade beams, and other items can take the final amount higher.
Piling cost for a 3-, 4-, or 5-storey building in Bangladesh
There is no safe way to price a 3, 4 or 5-storey house from floor count alone. For early
planning, the process should be simple. First complete the soil investigation. Then let the
structural engineer calculate column loads and foundation requirements. Once you know the pile
type, diameter, estimated depth and number of piles, contractors can quote the same scope. This
makes quotation comparison much easier.
For example, a low price per foot may look attractive until you discover that steel, concrete,
pile testing or rig mobilization is excluded. Another contractor may quote a higher rate but
include most of those items. Compare the total scope, not just one rate.
How to prepare a more accurate piling budget
Before requesting a final price, keep the soil report, structural drawings, pile schedule and
site location ready. Ask each bidder to quote against the same specification.
The quotation should also make clear whether boring or driving, reinforcement, concrete, casing,
pile head breaking, machinery, mobilization, testing, VAT and other charges are included.
That small step makes a big difference. You can compare like with like instead of choosing a low
rate that later grows through additional charges.
Planning piling and foundation work with Conspert Limited
Piling sits inside a much larger construction process. Soil investigation, structural design,
contractor coordination, budget control, and site supervision all need to work together.
If you are planning a project in Dhaka or elsewhere in Bangladesh, start with the site conditions
and engineering requirements first. Conspert Limitedcan
help
coordinate the construction process and develop a project-based budget after reviewing the
actual scope.
FAQs about piling cost in Bangladesh
Here are quick answers to some of the most common questions people ask about piling cost,
depth, soil testing, and foundation planning in Bangladesh.
RCC bored piling can roughly range from Tk 350 to Tk 1,600+ per running foot
based on diameter and project scope. Large piles, difficult soil, and deeper
drilling can cost more.
There is no single rate. For common residential-sized bored piles, public 2026
references show rates starting around Tk 350–600 per foot for smaller diameters
and increasing as diameter and specification rise.
It depends on the design and soil. A smaller bored pile may have a lower unit
rate, but choosing a pile only because it is cheaper is unsafe. The structural
and geotechnical requirements come first.
Pile depth depends on the soil profile and required capacity. Two nearby houses
can require different depths. Use the soil investigation and structural design
rather than a standard depth.
Not always, but access can increase the cost. Narrow roads, limited working
space, traffic restrictions and equipment setup can make some Dhaka sites more
difficult than open sites.
Not necessarily. Contractors often treat pile caps, grade beams and other
foundation work separately. Ask for an itemized quotation before comparing
prices.
Ideally, provide the soil report, structural pile schedule, pile diameter,
depth, quantity, concrete and reinforcement specifications, project location and
access details.
বিভিন্ন প্রকাশিত ঠিকাদারি মূল্যতালিকা অনুযায়ী, বাংলাদেশে RCC bored piling-এর
আনুমানিক খরচ প্রতি রানিং ফুট ৩৫০ থেকে ১,৬০০ টাকা বা তার বেশি হতে পারে। তবে
পাইলের ব্যাস, গভীরতা, মাটির অবস্থা এবং কাজের আওতার ওপর প্রকৃত খরচ নির্ভর করে।
প্রাথমিক বাজেট করা যায়, কিন্তু সেটি নির্ভরযোগ্য ফাইনাল নয়। Soil টেস্ট ছাড়া
প্রয়োজনীয় pile depth এবং foundation requirement সম্পর্কে নিশ্চিত হওয়া যায় না।
তাই final quotation নেওয়ার আগে soil investigation করা উচিত।
Need piling construction?
Contact Conspert Limited for reliable piling and foundation construction support.
Conspert offers integrated construction management in Dhaka for developers and businesses. Planning, design, execution & delivery made simple. Call: 01886-788890
Bashundhara is one of the several premium neighborhoods in Dhaka. In this article, we got into detail about the flat price in Bashundhara Residential Area.
The plot price in I Block of Bashundhara varies a lot depending on many factors like south-facing or not, corner plot or not, commercial or not, etc. Learn more.